Ratcliffe Hall – Christopher Newport University

Project Description

Wolf helped renovate an existing classroom to include a raised access floor with a ramp and handrails for Christopher Newport University’s new Server Room and Data Center. Work performed included: Renovation of an additional classroom to house Christopher Newport University’s Uninterruptible power supply (UPS) and Computer Room Air Conditioning (CRAC) Units. Modified existing fire sprinkler systems and alarms to meet local codes, and installed a new pre-action sprinkler system to serve both the data center and the ups room Modification of an existing landscape area into a courtyard with equipment pads. Installed a new 400 KW emergency back up generator, an automatic transfer switch (ATS), and a new 43.6 ton capacity air cooled modular chiller in the courtyard Work was performed while faculty and students occupied the surrounding classrooms and offices within the building during the school semester.

Poquoson Middle School Modernization

Project Description

As with most renovation projects, unexpected issues arise that require adjustments to timelines and budgets. This is the case with the Poquoson Middle School Modernization Project, but we’re determined to do the project right for future PMS students and staff. Due to challenges uncovered during the design phase of the project, the design plan and timeline must be adjusted, and additional funds have been allocated toward the project’s completion. The school will now be ready for occupancy in January 2023 instead of the planned re-occupancy in summer 2022, and the project’s total budget is now $19.45 million. The design team and architectural firm have been diligent in their work to identify costs upfront to meet educational needs and stay within available funding for the project. The identification of structural issues that affect the project’s planned design and the reallocation of funds within the project plan to meet design specifications are two of the major challenges that have affected timelines and budgets.

Seaford Elementary School

Project Description

The Scope of Work is generally comprised of phased renovations to Seaford Elementary School and several one-story additions, including a new classroom wing and expansions to the main entry/admin/media center and cafeteria/gym. Project improvements include the addition of 9 classrooms, a front entrance addition, and a stage addition onto the existing gymnasium, totaling approximately 19,165 square feet of new construction and renovation of the existing building (approx. 59,710 square feet). The renovation portion includes mechanical system upgrades, toilet upgrades, minor structural modifications, electrical upgrades, some existing roof repairs and interior finish upgrades. The proposed structures are expected to be of CMU wall construction that include brick veneer. The ground floor slab will be supported on grade. Existing pavement and playground areas will be demolished as necessary to facilitate construction. Site improvements include new asphalt driveways, parking, extended bus loop, courtyard, and playground (relocated).